Competition Without Coordination and How Market Structure Shapes U.S. Nuclear Energy

Competition Without Coordination and How Market Structure Shapes U.S. Nuclear Energy

PAYNE INSTITUTE COMMENTARY SERIES: STUDENT COMMENTARY

By Christian Luna

October 27, 2026

The United States has asked for more nuclear power and put the request in writing. In November 2024, the Biden administration set a goal of adding 200 gigawatts by 2050, roughly tripling the country’s nuclear capacity [1]. President Trump’s May 2025 executive order raised the ambition to 400 gigawatts in total, about four times today’s capacity [2]. Demand is giving those targets a stronger backdrop. The Energy Information Administration’s October 2026 outlook projects electricity consumption to grow about 2.2 percent this year and 1.6 percent next year [3]. But a forecast of more electricity use does not tell a supplier which reactor will be ordered, or when. The gap between those two kinds of confidence matters as much as the size of the target.

The United States knows how to build nuclear reactors. The harder question is whether it knows how to keep building them. A utility must commit billions before a plant earns anything, while the firms that supply it need enough future work to justify keeping their capabilities ready. Both decisions depend on electricity revenues that will arrive over decades. Different people hold these pieces, and they decide years apart. That makes the familiar argument over whether nuclear can succeed in a “free market” too simple. American electricity operates under several market arrangements, and none removes the need to connect today’s investment to tomorrow’s construction. The problem is how to organize that continuity without giving up the discipline that competition can provide.

The Cost Before the First Kilowatt Hour

Before a reactor sells a single kilowatt-hour, its owner may spend years paying for work that produces no electricity. The “overnight” capital cost used in many studies estimates what a plant would cost without the interest accumulated during construction. Nobody builds overnight. Borrowing costs keep growing while the plant cannot yet earn anything, so delays can hurt twice. Rework raises the physical bill while the owner keeps paying for money already spent. In their 2022 MIT study, nuclear engineers W. Robb Stewart and Koroush Shirvan examine how reactor design choices could reduce both construction costs and the risk of overruns [4]. That distinction is useful because a favorable estimate does not necessarily make a project financeable. An investor also needs reason to believe the estimate will survive construction.

Vogtle Units 3 and 4 in Georgia show why. The expansion was originally expected to cost about $14 billion and enter service in 2016 and 2017. By the time the second unit began operating in 2024, the estimated total exceeded $30 billion [5]. Federal financing helped the project reach completion, with the Department of Energy guaranteeing up to $12 billion in loans [6]. In an October 2026 interview, Julie Kozeracki, who leads DOE’s nuclear financing work, said the department calculated roughly $3 billion in interest savings for Georgia utility customers compared with commercial borrowing [7]. Those savings matter. They also coexist with the overruns. Lowering the price of money can improve a project’s economics without resolving the construction problems that made it expensive.

This is why financing belongs inside the cost discussion. An October 2026 study by Politecnico di Milano for Clean Air Task Force modeled European small modular reactor (SMR) deployment. In one sensitivity case, investors required a 12 percent return on their ownership stake instead of 6 percent. The modeled lifetime electricity cost rose from about €74 to €106 per megawatt-hour, while borrowing costs stayed at 4 percent [8]. That is roughly a 42 percent increase without changing the reactor. These are modeled results, not demonstrated SMR prices, but they show how much the financial arrangement can change the apparent competitiveness of the same technology. Investors charge for uncertainty, and the electricity must eventually pay that charge.

A lender financing one plant cannot rely on the average performance of an entire industry to cover that plant’s losses. A federal guarantee reduces the lender’s exposure, but it shifts some risk to the government rather than making the underlying project certain. For an unfamiliar reactor, even securing a long-term buyer may leave construction risk too uncertain for lenders without a financially strong sponsor willing to absorb overruns, a distinction Kozeracki emphasized [7]. Getting the first plant financed therefore answers only part of the question. Making the next plant easier to finance requires a delivery record that survives beyond the first project.

The Industry Between Projects

A nuclear reactor does not arrive as one finished product. A drawing becomes a plant through firms and workers that know how to meet nuclear quality requirements, often after years spent learning the work. DOE’s 2024 Advanced Nuclear Liftoff report describes Vogtle as a project that had to rebuild an industrial base after decades without a sustained construction program [9]. An industry, in this sense, is a kind of memory. It lives in people and habits more than in drawings, and it fades when it goes unused. Completing a plant preserves the asset. Preserving the ability to build another requires work for the people who have just learned how.

Consider a supplier deciding whether to expand its factory. The investment pays only if enough reactor orders follow, while a utility considering a reactor wants proof that suppliers can deliver on time and on price. Each waits for the other, and each is acting reasonably. This is the difficulty behind competition without coordination. A growing need for electricity does not, by itself, resolve it because that demand might be met by another technology or another reactor design. What matters to the supplier is a credible sequence of orders for the equipment it makes. Without that commitment, the next utility may face the same limited capacity and uncertainty that discouraged the first.

Repetition should help, but the American record shows that it does not happen automatically. Philip Eash-Gates and colleagues examined five decades of U.S. construction data and found that later plants were often more expensive than earlier ones. Factors outside the reactor hardware, including labor supervision, accounted for more than half the cost increase between 1976 and 1987 [10]. A comparison of French and American construction by economists Michel Berthélemy and Lina Escobar Rangel offers a more specific clue. They found statistically significant benefits from prior construction experience among similar reactors built by the same architect-engineer, the firm responsible for integrating the plant’s engineering [11]. Experience does not sit in a reactor’s name. The organizations doing the work have to carry it forward.

France also cautions against treating coordination as a guarantee. Its more centralized program used fewer designs than the American one, yet Arnulf Grubler’s 2010 study found substantial cost escalation [12]. Later research by Escobar Rangel and François Lévêque, using figures from France’s Court of Auditors, found a smaller increase associated with the move to larger reactors, alongside savings from repeating comparable designs [13]. The distinction matters. Coordination can help an industry retain what it learns while decisions to build larger or more complicated plants still raise costs. It does not eliminate poor management. What it offers is a better chance for the next project to reuse work already paid for, provided the design and the people delivering it remain sufficiently consistent.

Small modular reactors make that requirement especially important. A smaller unit can put less money at risk at once and move more work into a factory, but it can also give up the lower cost per unit of output available from a larger plant [9]. Its economic case therefore depends heavily on producing similar units repeatedly. A factory making one module every few years is a different business from one making the same module all year. The Politecnico study modeled a standardized fleet of 5–8 gigawatts capturing roughly half to two-thirds of the learning savings available in a fleet exceeding 50 gigawatts [8]. Those savings depend on the assumed learning actually occurring. They do not follow simply from calling a reactor modular.

The first buyer nevertheless bears costs that can benefit later buyers. Engineering completed for the first plant may be reused, and a supplier qualified for one project may serve the next. That creates a reason to share early costs across a group of customers. DOE’s Liftoff report calls for an initial committed orderbook of five to ten deployments of at least one design [9]. An orderbook means actual commitments to buy, with a sequence suppliers can plan around. It is a more useful measure of industrial readiness than a collection of interested customers who can all wait for someone else to go first. An expression of interest is not a production line.

Recent federal efforts are trying to close that gap. According to Westinghouse co-owner Cameco, DOE announced a June 2026 conditional commitment of up to $17.5 billion for long-lead components for as many as ten AP1000 reactors, the model used at Vogtle [14]. Buying equipment ahead of individual construction projects could give suppliers the demand they need to invest. Separately, the Nuclear Regulatory Commission proposed an October rule incorporating changes made during Vogtle’s construction into the AP1000’s standard design [15]. That would let future projects begin closer to what was actually built. Neither a conditional financing commitment nor a proposed rule proves that a fleet will be delivered, but both address continuity more directly than another announcement of national ambition.

The Market After Construction

Once a plant is operating, the risk changes. A reactor can run for many decades, while wholesale markets price electricity over days, hours and minutes. A market can tell an owner what a megawatt-hour is worth at three o’clock tomorrow afternoon. An investor deciding whether to build needs a credible view of earnings years after construction begins. Competitive markets can support long-term contracts, so this difference in timing does not mean they are inherently incompatible with nuclear. It does mean that the spot price, the price for near-term delivery, is only part of the investment case. The arrangement that makes future revenue dependable matters too.

Where that risk lands depends on the institutions around the plant. Restructuring spread across parts of the United States in the 1990s, after most of the nuclear fleet had been ordered under regulated utility arrangements [16]. In Georgia, a utility can recover approved costs through customer rates, subject to regulatory review. That makes customers part of the financing arrangement, while shareholders can still bear costs regulators exclude. In December 2023, Georgia’s commission limited recovery of Georgia Power’s capital costs for Vogtle 3 and 4 to $7.562 billion, against the company’s expected $10.75 billion share [17]. Those figures concern Georgia Power, not the entire project. They show why describing a plant as either publicly supported or privately financed misses how its risks are actually divided.

An operating reactor and a proposed one also face different decisions. Low fuel costs can help an existing plant compete, but its revenue still has to cover staffing and maintenance. A new project must cover those expenses as well as repay construction. Three Mile Island Unit 1 in Pennsylvania illustrates the difference between operating well and earning enough. Constellation reports that it achieved a 96.3 percent capacity factor in its last year before closing for economic reasons in 2019. In 2024, the company announced a planned restart supported by a twenty-year power purchase agreement with Microsoft [18]. A capacity factor measures output against what continuous full-power operation could produce. That strong performance had not secured the plant’s finances. The contract gave its owner a different basis for investing, although a restart also requires physical work and regulatory approval.

American wholesale markets provide different kinds of revenue. ERCOT’s energy-only market in Texas relies on energy prices and payments for services that help balance the grid, alongside private contracts [19]. PJM, which operates the grid across parts of the eastern United States, also has a capacity market that pays resources to commit to being available during a future delivery period [20]. Those payments can help cover fixed costs, but they do not establish a dependable electricity price for decades. Nor does an energy-only market prevent a generator from signing a long contract. The relevant question for nuclear is what combination of revenues a project can secure before asking investors to fund construction.

Calling every unfavorable result a market failure would weaken that argument. A 2018 study by MIT researcher Jesse Jenkins found falling gas prices were the main driver of lower power prices at nineteen nuclear stations in PJM during 2008–2016 [21]. That is competitive pressure, even when it makes a reactor less profitable. A separate question is whether market prices fully reflect the value society places on avoiding emissions. Support justified by that public benefit should explain what it buys, just as support for early construction should explain who benefits from the learning. The International Atomic Energy Agency’s 2026 deployment outlook describes long-term contracts and public financing as ways to make nuclear revenues more predictable [22]. They can help a project proceed, but making risk acceptable to an investor does not make it disappear. Customers or taxpayers may be taking on part of it.

What Coordination Should Buy

The United States already supports nuclear through public financing and research, and its electricity rules shape what plants can earn. More support, by itself, is therefore an incomplete answer. The question is whether that support leaves the industry better able to deliver the next plant. Competition is valuable when buyers compare designs and test whether the promised benefits justify the costs. Once customers commit to a design, however, repeatedly reopening engineering decisions can consume the savings repetition was meant to provide. “Design one, build many” asks for enough stability to reuse completed work, with changes justified by safety needs or demonstrated benefits rather than the assumption that every project must be different.

That stability should still leave room for pressure on cost and performance. Suppliers can compete for repeat work under common specifications, while buyers compare delivery results across projects. But replacing the firms that hold experience simply to obtain the lowest initial bid can undermine the learning the program is meant to purchase. The research on architect-engineer continuity makes that tension difficult to ignore [11]. A coordinated orderbook should give capable builders reason to retain their crews while making them answer for what they deliver. The financial side needs similar discipline. A long-term electricity buyer can stabilize revenue, but someone must still be responsible when construction runs late. Those responsibilities belong in the agreements that make a project possible.

Public backing should be judged against that concrete exchange. If later reactors are expected to be cheaper, the case should identify who is likely to order them and what work they will actually reuse. Progress should be measured in commitments and delivery experience, not only in designs tested or capacity announced. The country does not need one reactor design for every application, but each design’s claim to lower costs through repetition needs a plausible production run behind it. Otherwise, public support can keep paying for first projects without creating the conditions for a second. A successful demonstration is valuable, but its industrial value depends on what happens afterward.

When Vogtle Unit 4 entered commercial operation in 2024, EIA noted that no nuclear reactors were under construction in the United States [5]. That was a description of that moment, but it captures the vulnerability. A country can keep its blueprints and lose its hands. Markets coordinate across time only when someone has a reason to make the next commitment before the existing capability disappears. Growing electricity demand makes that commitment more plausible. It cannot substitute for it. The question to ask of any nuclear policy is whether building one reactor leaves the country better able to build the next.

References

[1] U.S. Department of Energy. U.S. Sets Targets to Triple Nuclear Energy Capacity by 2050. November 12, 2024.

[2] The White House. Ordering the Reform of the Nuclear Regulatory Commission. Executive Order 14300, May 23, 2025, section 2(c).

[3] U.S. Energy Information Administration. Short-Term Energy Outlook. October 2026, Table 7a. Growth rates calculated from total consumption of 4,195, 4,288 and 4,356 billion kWh in 2025–2027.

[4] Stewart, W. Robb, and Koroush Shirvan. Capital Cost Evaluation of Advanced Water-Cooled Reactor Designs With Consideration of Uncertainty and Risk. MIT CANES Report 194, June 2022.

[5] U.S. Energy Information Administration. Plant Vogtle Unit 4 Begins Commercial Operation. May 1, 2024.

[6] U.S. Department of Energy. “Secretary Perry Announces Financial Close on Additional Loan Guarantees During Trip to Vogtle Advanced Nuclear Energy Project.” March 22, 2019. Republished in Georgia Power’s news archive.

[7] Bordoff, Jason, interviewing Julie Kozeracki. DOE’s Julie Kozeracki on the Federal Role in US Nuclear Financing. Columbia Energy Exchange, October 20, 2026, transcript at 22:39–28:58. Interest savings are DOE’s estimate.

[8] Locatelli, Giorgio, et al. From Fragmentation to Fleet: A European Blueprint for Coordinated SMR Deployment. Politecnico di Milano for Clean Air Task Force, October 2026, pp. 5 and 83–84. Model estimates depend on financing and learning assumptions.

[9] U.S. Department of Energy. Pathways to Commercial Liftoff: Advanced Nuclear. September 2024, especially pp. 40–41, 47–54 and 71–73.

[10] Eash-Gates, Philip, et al. Sources of Cost Overrun in Nuclear Power Plant Construction Call for a New Approach to Engineering Design. Joule 4, no. 11 (2020), 2348–2373. DOI 10.1016/j.joule.2020.10.001.

[11] Berthélemy, Michel, and Lina Escobar Rangel. Nuclear Reactors’ Construction Costs: The Role of Lead-Time, Standardization and Technological Progress. Energy Policy 82 (2015), 118–130. DOI 10.1016/j.enpol.2015.03.015.

[12] Grubler, Arnulf. The Costs of the French Nuclear Scale-Up: A Case of Negative Learning by Doing. Energy Policy 38, no. 9 (2010), 5174–5188. DOI 10.1016/j.enpol.2010.05.003.

[13] Escobar Rangel, Lina, and François Lévêque. Revisiting the Cost Escalation Curse of Nuclear Power: New Lessons from the French Experience. Economics of Energy & Environmental Policy 4, no. 2 (2015). DOI 10.5547/2160-5890.4.2.lran.

[14] Cameco Corporation. 2026 Second Quarter Report. Management’s discussion and analysis, section on DOE American Nuclear Supply Chain Loans. SEC Form 6-K exhibit 99.2. Conditional commitment, not completed financing.

[15] U.S. Nuclear Regulatory Commission. AP1000 Design Certification Renewal. Proposed rule, Federal Register 91, October 14, 2026, 65133–65137. Proposal status as of October 24, 2026.

[16] Borenstein, Severin, and James Bushnell. The US Electricity Industry After 20 Years of Restructuring. Annual Review of Economics 7 (2015), 437–463. DOI 10.1146/annurev-economics-080614-115630.

[17] Georgia Public Service Commission. Commissioners Approve Agreement for Vogtle Construction Costs. December 19, 2023. Recovery figures concern Georgia Power’s share of project capital costs.

[18] Constellation Energy. Constellation to Launch Crane Clean Energy Center, Restoring Jobs and Carbon-Free Power to the Grid. September 20, 2024. Company announcement; restart subject to approvals.

[19] Electric Reliability Council of Texas. ERCOT Grid Insights: Energy-Only Wholesale Market. October 2025.

[20] Federal Energy Regulatory Commission. An Introductory Guide for Participation in PJM Processes. Updated April 11, 2025, sections on energy and capacity markets.

[21] Jenkins, Jesse D. What’s Killing Nuclear Power in US Electricity Markets? Drivers of Wholesale Price Declines at Nuclear Generators in the PJM Interconnection. MIT Center for Energy and Environmental Policy Research, January 2018.

[22] International Atomic Energy Agency. Global Nuclear Power Development Outlook: Infrastructure, Financing and SMR Technology. October 2026, pp. 12–17 on financing and market risk.

 

 

ABOUT THE AUTHOR

Christian Luna
BS, Mechanical Engineering – Focus in Nuclear Energy with a Minor in Public Affairs

Christian Luna is a mechanical engineering student and Energy Scholar at the Colorado School of Mines. His research focuses on the systems-level dynamics of global energy and security, with emphasis on how physical infrastructure, industrial capacity, and geopolitical strategy interact within critical energy networks. His work examines the interdependencies between energy systems, defense-relevant supply chains, and emerging technologies, including nuclear scale-up, critical minerals, and energy transition infrastructure. He approaches these domains through a systems-thinking lens, with attention to how technological constraints and geopolitical risk shape the stability and resilience of global energy structures.

ABOUT THE PAYNE INSTITUTE

The mission of the Payne Institute at Colorado School of Mines is to provide world-class scientific insights, helping to inform and shape public policy on earth resources, energy, and environment. The Institute was established with an endowment from Jim and Arlene Payne and seeks to link the strong scientific and engineering research and expertise at Mines with issues related to public policy and national security.

The Payne Institute Commentary Series offers independent insights and research on a wide range of topics related to energy, natural resources, and environmental policy. The series accommodates three categories namely: Viewpoints, Essays, and Working Papers.

Visit us at www.payneinstitute.mines.edu

FOLLOW US

 

 

DISCLAIMER: The opinions, beliefs, and viewpoints expressed in this article are solely those of the author and do not reflect the opinions, beliefs, viewpoints, or official policies of the Payne Institute or the Colorado School of Mines.